Order to authorize and approve Contractor’s Estimate Package #2 from Simmons Erosion Control for $17,546.26 on the Mary Ann Drive Sidewalk Project.

Report Passed Introduced October 18, 2024

What this record is

Held by
Simmons Erosion Control 3 records across this site
Amount
$18K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Simmons Erosion Control also holds

Order to authorize and approve payment of Contractor’s Estimate #1 from Simmons Erosion Control, Inc. for $301,394.86 on the Mary Ann Drive Sidewalk p… $301K Pearl, MS Consider an Order to adopt a Resolution accepting the bid of Simmons Erosion Control for the Mary Ann Drive Sidewalk Installation, finding that the co… $272 Pearl, MS
Committee
Mayor and Board of Aldermen
Requested by
Special Projects
Introduced
October 18, 2024
On agenda
November 5, 2024
Passed
November 5, 2024

Where it was heard

Mayor and Board of Aldermen Nov 5, 2024 approve Pass