26-0872
ORDER approving Change Order 4 with DNA Underground, LLC., for the MCWI/ARPA Hwy 67 / Tradition Area Pump Station project adding work to decommission the old S. Carr Lift Station, adding a canopy over the control panels, and a concrete driveway addition, all to be completed within the original project budget, as recommended by BMA and Jaclyn Turner, County Engineer, and authorizing the Board President to execute documents.
What this record is
- Held by
- DNA Underground, LLC 10 records across this site
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
DNA Underground, LLC also holds
ORDER approving final project closeout documents for ARPA/MCWI Firetower Water Project with DNA Underground, LLC., as recommended by Chiniche Engineer… ORDER approving final project closeout documents for ARPA/MCWI Hwy 67/Tradition Area Sewer Project with DNA Underground, LLC., as recommended by BMA a… ORDER approving Final Summary Change Order 1 with DNA Underground, LLC for the MCWI/ARPA Superior Utilities Lagoon project, resolving final contract a… ORDER approving Change Order #3 with DNA Underground, LLC for the ARPA Hwy 67 / Tradition Area Regional Sewer Expansion Project, adding materials, equ… ORDER approving Change Order 2 for the ARPA / MCWI Firetower Road Water System project with DNA Underground, LLC, to include fire line connection at t…All 10 records for DNA Underground, LLC →
- Committee
- Engineering
- Introduced
- May 27, 2026
- On agenda
- June 1, 2026
- Passed
- June 1, 2026