26-0849
ORDER approving Change Order 4 with Specialty Contractors & Assoc., Inc., for the MCWI/ARPA Beach Outfall Repairs & Upgrades project, adding outfall locations to the contract and reducing the contract time to align with state funding limitations. Change Order increases contract value by $1,044,725.10 and reduces contract time by 37 days, recommended by BMA and Jaclyn Turner, County Engineer, and authorizing the Board President to execute documents.
What this record is
- Held by
- Specialty Contractors & Assoc., Inc 3 records across this site
- Amount
- $1.04M
- Runs until
- no end date published in this record
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
Specialty Contractors & Assoc., Inc also holds
ORDER approving final project closeout documents for ARPA/MCWI Beach Outfalls Project with Specialty Contractors & Assoc., Inc., as recommended by BMA… ORDER spreading upon the minutes the following executed documents: a) Construction Change Directive No. 3 for J.W. Puckett & Co.'s contract for the Ha…- Committee
- Engineering
- Introduced
- May 26, 2026
- On agenda
- June 1, 2026
- Passed
- June 1, 2026