26-0696

ORDER approving construction change directives for work at the Harrison County Diversion Center & Health Department, as recommended by Eley Guild Hardy Architects, and authorizing the Board President to execute same: a) Change No. 1 for a decrease in the amount of $53,121.82 to the contingency allowance to J.W. Puckett & Co.’s contract for listed changes. b) Change No. 2 for a decrease in the amount of $54,930.00 to the contingency allowance to J.W. Puckett & Co.’s contract for listed changes.

Order Passed Introduced April 28, 2026

What this record is

Amount
$53K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
County Administrator Office
Introduced
April 28, 2026
On agenda
May 4, 2026
Passed
May 4, 2026