docketcity.com
26-0427

ORDER awarding contract for construction of the Warm Up Arena Extension at the Harrison County Fairgrounds to the lowest and best bidder, Clymer Contracting, in the total amount of $439,870.00, finding that the bid submitted by Twin L Construction was not responsive because it was a bid form for another project and should therefore be rejected, and authorizing the Board President to execute contract documents upon receipt, as recommended by the County Engineer. [DETAILED ORDER FOLLOWS AS ATTACHMENT 1.]

Order Passed Introduced March 9, 2026

What this record is

Amount
$440K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Engineering
Introduced
March 9, 2026
On agenda
March 9, 2026
Passed
March 9, 2026