ORDER approving Change Order #3 with Holden Earth Moving and Construction Co. Inc. for the ARPA Bells Ferry Road Elevation - Drainage and Flood Access Project, adjusting items to reflect field shoulder conditions at pipe crossings and removing quantities of items not needed, resulting in a reduction of the contract in the amount of $5,456.00, as recommended by Covington Civil & Environmental and Jaclyn Turner, County Engineer, and authorizing the Board President to execute the documents.
What this record is
- Held by
- Holden Earth Moving and Construction Co 6 records across this site
- Amount
- $5K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Holden Earth Moving and Construction Co also holds
ORDER approving final project closeout documents for ARPA/MCWI Bells Ferry Road Elevation and Drainage Project with Holden Earth Moving and Constructi… ORDER approving Change Order 4 with Holden Earth Moving and Construction Co., Inc., for the Bells Ferry Road Elevation - Drainage and Flood Access ARP… ORDER approving Change Order 2 for the ARPA / MCWI Bells Ferry Road Elevation - drainage project with Holden Earth Moving and Construction Co., Inc., … ORDER spreading upon the minutes the following executed documents: a) Mississippi Department of Environmental Quality Sub-Award Agreement Modification… ORDER approving Change Order 1 with Holden Earth Moving and Construction Co., Inc., for the ARPA/MCWI Bells Ferry Road Elevation - Drainage and Flood …- Committee
- Engineering
- Introduced
- March 3, 2026
- On agenda
- March 9, 2026
- Passed