25-1856
ORDER approving Change Order 1 with Dan Hensarling, Inc., for the installation of additional outlets in various rooms as requested by end user and as recommended by the architect, MP Design Group. Change order will add $1,690.00 to the contract. Grant funds are available for 100% of the cost. Authorize Board President to execute included documents for the IDD Mental Health building project.
What this record is
- Held by
- Dan Hensarling, Inc 4 records across this site
- Amount
- $2K
- Runs until
- no end date published in this record
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
Dan Hensarling, Inc also holds
ORDER authorizing payment of the following claims: a) $141,386.60 to Dan Hensarling, Inc., Pay Application No. 3 for Harrison County IDD Building, pay… ORDER approving payment of claims listed: a) $24,164.58 to Total Health, LLC, Invoice No. 022025-HC, Health Care service for March 2025, payable from … ORDER awarding the ARPA IDD Mental Health Building Construction project to the lowest and best bidder in accordance with the recommendation of the pro…- Committee
- Engineering
- Introduced
- September 30, 2025
- On agenda
- October 6, 2025
- Passed
- October 6, 2025