ORDER accepting and approving Final Pay Application No. 6, Summary Change Order to reflect actual quantities used on the project, and all closeout documents for the Pump Station for the Tradition Medical City DIP Grant No. 432 Project with Bottom 2 Top Construction, LLC., as recommended by BMA as attached. Authorize Final Payment in the amount of $9,530.19 and authorize Board President to execute all included documents.
What this record is
- Held by
- Bottom 2 Top Construction, LLC 10 records across this site
- Amount
- $10K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
- Compared to
- $107K – $549K the middle half of 7 other Bottom 2 Top Construction, LLC contracts; median $348K — this one sits well outside that, which a longer term or wider scope will do, but is worth reading
construction contracts in MS that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Bottom 2 Top Construction, LLC also holds
ORDER spreading upon the minutes the following executed documents: a) Change Order #2 with Bottom 2 Top Construction, LLC, for the MCWI/ARPA Beatline … ORDER approving the attached revised Change Order #2 with Bottom 2 Top Construction, LLC, for the MCWI/ARPA Beatline Road Sewer Collection System proj… Resolution - approving Change Order No. 1 to Contract with Bottom 2 Top Construction, LLC, for the Northwood Hills Water Main Replacement Project, and… ORDER approving final project closeout documents for ARPA/MCWI Beatline Road Sewer Project with Bottom 2 Top Construction, LLC., as recommended by Cov… Authorize Closeout Package – Construction – Washington Avenue Utility Improvements / Front Beach Drive to Lafontaine Avenue – Tidelands and GOMESA Fun…All 10 records for Bottom 2 Top Construction, LLC →
- Committee
- Engineering
- Introduced
- July 29, 2025
- On agenda
- August 4, 2025
- Passed
- August 4, 2025
Watch what Harrison County buys
This is one award. Harrison County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.