25-1067

ORDER approving Change Order No. 1 with J.E. Talley Construction, Inc., to add erosion control blanket and riprap in areas with increased erosion issues identified during construction. Guardrail terminal ends are also being modified and weather impact to construction time is included, resulting in a contract increase of $27,908.80 and 28 additional days. Authorize Board President to execute documents.

Order Passed Introduced June 4, 2025

What this record is

Held by
Talley Construction, Inc
Amount
$28K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Engineering
Introduced
June 4, 2025
On agenda
June 9, 2025
Passed