25-0435

ORDER approving the final plat and related documents as listed below for Hatten Manor Subdivision, Phase 1, (90 lots), Section 22, Township 6 South, Range 11 West, Supervisor's Voting District 5, First Judicial District, as recommended by Jaclyn Turner, P.E., Harrison County Engineer, and authorizing the Board President to execute same: a) Final Plat (90 lots) b) Final Plat Recording fee, Check No. c) City of Gulfport Approval Letter, dated March 3,2025 d) MDEQ Approval Letter, dated 01/31/2025 e) MSDH Approval Letter, dated 02/20/2025 f) Mississippi Power Company Lighting Agreement g) Covenants h) Street Names Approval i) Maintenance Bond j) Lift of Asphalt Bond k) Completion Bond - $75,000.00 l) Personal Guarantee

Order Passed Introduced March 5, 2025
Committee
Engineering
Introduced
March 5, 2025
On agenda
March 10, 2025
Passed
March 10, 2025