25-0316
ORDER accepting and approving closeout documents related to the ARPA / MCWI Canal Road Water Main Connector project, including the final summary change order reflecting a contract reduction of $9,026.15, and the contractor’s final pay application in the amount of $105,745.60, with authorization for payment of the final application and for the Board President to execute the same.
What this record is
- Amount
- $106K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Engineering
- Introduced
- February 19, 2025
- On agenda
- March 3, 2025
- Passed
- March 3, 2025