ORDER acknowledging receipt of FEMA Determination Memo for Hurricane Zeta repair project PW # 389, Jim Simpson Pier. FEMA’s decision is that the Mitigation Proposal (rebuild with concrete) is determined not cost-effective (exceeding 15% of rebuilding to pre-Zeta condition), and the reimbursement amount of Mitigation Proposal will be capped at $2,144,212.50 total project cost.