24-4785
ORDER awarding the bid for the ARPA/MCWI project for the Bells Ferry Road Elevation - Drainage and Flood Access project to the lowest and best bidder, Holden Earth Moving & Construction Co. for the base bid and all additive alternates for a total award of $8,524,656.60, as recommended by the Design Engineer Covington Civil & Environmental, and the County Engineer Jaclyn Turner, and authorize the Board President to execute contracts following legal review. [DETAILED ORDER FOLLOWS AS ATTACHMENT 1.]
What this record is
- Amount
- $8.52M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Engineering
- Introduced
- December 12, 2024
- On agenda
- December 19, 2024
- Passed
- December 19, 2024