24-3960
ORDER awarding the contract for the ARPA MCWI funded Herman Ladner Road Elevation - Drainage and Flood Access project to the lowest responsive bid of Holliday Construction, LLC., in the amount of $995,755.60, as recommended by Digital Engineering & Imaging, Inc., the design engineer, and Jaclyn Turner, County Engineer, and authorize Board President to execute all contract documents following legal review of same. [DETAILED ORDER FOLLOWS AS ATTACHMENT 1.]
What this record is
- Held by
- Digital Engineering & Imaging, Inc 5 records across this site
- Amount
- $996K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Digital Engineering & Imaging, Inc also holds
ORDER approving Contract Closeout documents, including the Final Summary Change Order #4 with Apple Construction for the ARPA/MCWI Flatbranch Regional… ORDER approving Change Order 3 with Apple Construction for the Flatbranch Regional Pump Station project, authorizing changes relating to various permi… ORDER approving payment of claims listed: a) $52,155.25 to Southern Mississippi Planning & Development District, Invoice No. 13189, Annual Membership … ORDER awarding the contract for the ARPA MCWI funded Flatbranch Regional Pump Station project to the lowest responsive bid of Apple Construction Co., …- Committee
- Engineering
- Introduced
- August 6, 2024
- On agenda
- August 12, 2024
- Passed
- August 12, 2024