ORDER approving Change Order No. 01, dated June 21, 2024 with Benecorp Incorporated, for the Multi Department Complex, Metal Building at HARCO, for an increase of $4,977.05, for foundation work increase in concrete and rebar quantities following the contractor's provision of final building reactions for the foundation and plumbing work for the addition of floor drains, and authorizing the Board President to execute the same, as recommended by Jaclyn Turner, P.E., Harrison County Engineer.
What this record is
- Held by
- Benecorp Incorporated
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Engineering
- Introduced
- June 24, 2024
- On agenda
- July 1, 2024
- Passed
- July 1, 2024