260587
Sponsor: Director of Water Services Department Authorizing the Director of Water Services to execute a $7,953,132.45 construction contract with Leath & Sons, Inc., for the Water Main Replacement in the Area of Smart Avenue to Van Brunt Boulevard, E. 14th Street to Jackson Avenue project; authorizing a maximum expenditure of $8,748,445.70; and recognizing this ordinance as having an accelerated effective date. Advance and Do Pass
What this record is
- Held by
- Leath & Sons, Inc 13 records across this site
- Amount
- $8.75M
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Leath & Sons, Inc also holds
Sponsor: Director of Water Services Department Authorizing the Director of Water Services to execute a $2,700,000.00 construction contract with Leath … Sponsor: Director of Water Services Department Authorizing the Director of Water Services to execute a $2,000,000.00 construction contract with Leath … Consideration of an award of contract to Leath & Sons, Inc. for the Main 11 Emergency Sanitary Sewer Rehabilitation Project, PN 1-R-004-23. Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Leath & Sons, Inc. for construction of the Grant Street Waterline Im… Consideration of Engineer’s Estimate, acceptance of bids and award of contract to Leath & Sons, Inc. for construction of the Brougham Village Sanitary…All 13 records for Leath & Sons, Inc →
- Committee
- Council
- Introduced
- June 24, 2026
- On agenda
- July 9, 2026
- Passed
- July 9, 2026