Approval of the 1st change order to an agreement between Genesee County and Granger Construction Company, in the amount of $2,500,000.00, for a revised total of $15,668,000.00, to allow for additional construction services in support of the Flint Riverfront Restoration Project; the funding for this amendment will be paid from account 2088-770.32-801.028 and requires no additional appropriation
What this record is
- Amount
- $2.50M
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
construction contracts in MI that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Public Works Committee
- Requested by
- Public Works Committee
- Introduced
- November 5, 2024
- On agenda
- December 4, 2024
- Passed
- December 4, 2024
Where it was heard
Public Works CommitteeWatch what Genesee County buys
This is one award. Genesee County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.