docketcity.com
25-0098

Requesting approval of a time-only contract extension of three years for MWH Contractors Inc. for construction manager at risk services on the Poplar Street Pump Station project.

Mayor's Request Approved Introduced January 14, 2025

What this record is

Held by
MWH Contractors Inc
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Engineering
Introduced
January 14, 2025
On agenda
January 23, 2025
Passed
February 24, 2025
Enacted
February 13, 2025
Enactment no.
218331

Where it was heard

City Council Feb 13, 2025 Approved Pass Finance Committee Feb 11, 2025 Recommended to be approved Pass City Council Jan 23, 2025 Referred for recommendation