Consideration of an Agreement with Garney Companies, Inc. for pre-construction phase services for the Cedar Creek WWTP Expansion Phase 2, PN 1-C-013-25, and the Cedar Creek WWTP Solids Handling Rehabilitation Projects, PN 1-C-025-25.

Council Consent Passed Introduced March 17, 2025

What this record is

Held by
Garney Companies, Inc 18 records across this site
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Garney Companies, Inc also holds

North Higley Lift Station and Thomas Road Sewer project - Guaranteed Maximum Price (GMP) No. 1 of 1 (District 5) The North Higley Lift Station and Tho… $8.00M Mesa, AZ Request approval to correct Agenda Item No. 25-0978 to correct the contracting entity’s name for the award of 25RFP021025K-CRB, Progressive Design/Bui… Fulton County, GA North Higley Lift Station and Thomas Road Sewer Project - Northeast Mesa, Construction Manager at Risk (CMAR) (District 5) The North Higley Lift Stati… $285K Mesa, AZ One-Reading ordinance authorizing Amendment No. 2 to the Construction Manager-At-Risk (CMAR) contract with Garney Companies, Inc. of Kansas City, Miss… $294.0M Corpus Christi, TX Consideration of Amendment No. 1 with Garney Companies, Inc. for equipment procurement for the Super Critical Water Oxidation Pilot Project, PN 1-C-01… Olathe, KS

All 18 records for Garney Companies, Inc →

Committee
City Council
Requested by
Public Works
Introduced
March 17, 2025
On agenda
April 1, 2025
Passed
April 1, 2025

Where it was heard

City Council Apr 1, 2025 approved Pass