22-417

Communication from the City Manager and Director of Public Works with a Request to APPROVE Change Order 1 to the Storm Drainage Repair Annual CONTRACT with J.C. DILLON, INC., and to Authorize the City Manager to Execute the Extension to Increase the Original Contract not to exceed the Limit by $1,350,000.00, for a Total of $2,350,000, and extend the Completion Date to February 14, 2024. (Reference Item No. 22-046) (All Council Districts)

Agreement Approved Introduced November 17, 2022

What this record is

Amount
$2.35M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Public Works
Introduced
November 17, 2022
On agenda
December 13, 2022
Passed
December 13, 2022

Where it was heard

City Council Dec 13, 2022 approved Pass