Communication from the City Manager and Director of Public Works with a Request to Authorize a Change Order #1B for a $750,000 Extension of the 2019 STORM SEWER REPAIR CONTRACT with J.C. DILLON, INC., and to Authorize the City Manager to Execute the Change Order to add $750,000 to the budget for a Total 2021 Budget Amount of $1,650,000.00 (Reference 19-059,19-142, and 21-029) [All Council Districts]

Contract Approved Introduced July 7, 2021

What this record is

Amount
$1.65M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Public Works
Introduced
July 7, 2021
On agenda
August 10, 2021
Passed
August 10, 2021