docketcity.com
19-006

Communication from the City Manager and Interim Director of Public Works with a Request to APPROVE Change Order #2 for an Additional Amount of $30,000.00 for the Concrete Vertical Repairs CONTRACT - 2017 Project with ILLINOIS CIVIL CONTRACTORS INC., for a Total Amended Contract Amount of $480,000.00. (Ref. Item 17-228 and 18-177) (All Council Districts)

Contract Approved Introduced January 3, 2019

What this record is

Held by
Illinois Civil Contractors INC 5 records across this site
Amount
$480K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Illinois Civil Contractors INC also holds

Communication from the City Manager and Director of Public Works with a Request to APPROVE Change Order #1 for a One-Year Extension of the CONCRETE RE… $100K Peoria, IL ends Jun 13, 2023 Communication from the City Manager and Interim Director of Public Works with a Request for Approval of the Following Items: A. APPROVE Change Order #… $22K Peoria, IL Communication from the City Manager and Director of Public Works with a Request to APPROVE the Following: A) CHANGE ORDER #1 for an Additional Amount … $450K Peoria, IL Communication from the City Manager, Finance Director/Comptroller and Director of Public Works with a Request for the following; A. ADOPT an ORDINANCE… $36K Peoria, IL
Committee
City Council
Requested by
Public Works
Introduced
January 3, 2019
On agenda
January 8, 2019
Passed
January 8, 2019