Communication from the City Manager and Director of Public Works with a Request to Accept the LOW BID of HOROWITZ CONCRETE COMPANY, in the Amount of $210,240.45, and Award a CONTRACT for the SIDEWALKS IN NEED OF REPAIR 2018 PROJECT, with an Additional Authorization of $19,759.55, for a Total Contract Award of $230,000.00. NEW COMMUNICATION (Council District 1)

Contract Approved Introduced August 15, 2018

What this record is

Amount
$210K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Public Works
Introduced
August 15, 2018
On agenda
August 28, 2018
Passed
August 28, 2018