Communication from the City Manager and Director of Public Works with a Request to Authorize Change Order #1 for a One-Year Extension of the 2017 Annual Drainage Repair CONTRACT with HOERR CONSTRUCTION to February 9, 2019, and to Authorize the City Manager to Execute the Change Order, for a Total Budget Amount of $400,000.00. (Reference 17-021) (All Council Districts)

Contract Approved Introduced December 28, 2017

What this record is

Held by
Hoerr Construction 21 records across this site
Amount
$400K
Runs until
December 28, 2018 already ended calculated from the contract term stated in the record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Hoerr Construction also holds

Sewer Lining Program, Change Order No. 1 Reflecting an increase to the contract with Hoerr Construction, Inc. in the amount of $51,610.00. This increa… $52K Lombard, IL Subject: Bid Opening Results for Contract 2026-WW-SS-03, Sanitary Sewer Lining Project Staff Recommendation: To Approve Fiscal Note: Lowest responsive… $351K Racine, WI Recommendation for the approval of a contract with Hoerr Construction, Inc., for the Prairie Avenue Pipe Rehabilitation Project, for Stormwater Manage… $48K DuPage County, IL ends Nov 30, 2026 Approve the award of Change Order #1 to Contract 25-047, Sanitary Sewer Mainline Cleaning, to Hoerr Construction, Inc. for the amount not to exceed $2… $225K Naperville, IL Sanitary Sewer Lining Program Request for a waiver of bids and award of a contract to Hoerr Construction, Inc., the lowest proposal of four (4) receiv… $888K Lombard, IL

All 21 records for Hoerr Construction →

Committee
City Council
Requested by
Public Works
Introduced
December 28, 2017
On agenda
January 9, 2018
Passed
January 9, 2018