18-003
Communication from the City Manager and Director of Public Works with a Request to Authorize Change Order #1 for a One-Year Extension of the 2017 Annual Drainage Repair CONTRACT with HOERR CONSTRUCTION to February 9, 2019, and to Authorize the City Manager to Execute the Change Order, for a Total Budget Amount of $400,000.00. (Reference 17-021) (All Council Districts)
What this record is
- Held by
- Hoerr Construction 21 records across this site
- Amount
- $400K
- Runs until
- December 28, 2018 already ended calculated from the contract term stated in the record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Hoerr Construction also holds
Sewer Lining Program, Change Order No. 1 Reflecting an increase to the contract with Hoerr Construction, Inc. in the amount of $51,610.00. This increa… Subject: Bid Opening Results for Contract 2026-WW-SS-03, Sanitary Sewer Lining Project Staff Recommendation: To Approve Fiscal Note: Lowest responsive… Recommendation for the approval of a contract with Hoerr Construction, Inc., for the Prairie Avenue Pipe Rehabilitation Project, for Stormwater Manage… Approve the award of Change Order #1 to Contract 25-047, Sanitary Sewer Mainline Cleaning, to Hoerr Construction, Inc. for the amount not to exceed $2… Sanitary Sewer Lining Program Request for a waiver of bids and award of a contract to Hoerr Construction, Inc., the lowest proposal of four (4) receiv…All 21 records for Hoerr Construction →
- Committee
- City Council
- Requested by
- Public Works
- Introduced
- December 28, 2017
- On agenda
- January 9, 2018
- Passed
- January 9, 2018