docketcity.com
17-108

Communication from the City Manager and Director of Public Works with a Request to ACCEPT the LOW BID of R.A. CULLINAN & SONS, a Division of United Contractors Midwest, Inc., and Award a Construction CONTRACT, in the Amount of $2,067,480.87, which is the Base Bid of $1,879,528.06 plus 10% for contingency, for the HARVARD AVE. PHASE 1 - SHADY OAK DRIVE to PURDUE STREET RECONSTRUCTION PROJECT. (Council District 3)

Contract Approved Introduced April 13, 2017

What this record is

Amount
$2.07M
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Public Works
Introduced
April 13, 2017
On agenda
April 25, 2017
Passed
April 25, 2017