Approve the award of Change Order #1 to Work Order 22-067-WATER-25-03, Construction Engineering Services - Fairway and Country Lakes Water Main Improvements, to Crawford, Murphy & Tilly, Inc. for an amount not to exceed $11,600.00, for a total award of $109,770.00 and an additional 242 calendar days

Procurement Change Order Passed Introduced January 13, 2026

What this record is

Held by
Crawford, Murphy & Tilly, Inc 18 records across this site
Amount
$12K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Crawford, Murphy & Tilly, Inc also holds

Engineering Agreement Supplement #1: Auburn Street over Kent Creek Bridge Replacement (Land Acquisition) to Crawford, Murphy & Tilly, Inc., of Rockfor… $581K Rockford, IL ends Dec 31, 2027 Engineering Agreement Supplement #2: Auburn Street Corridor Improvements (Land Acquisition - Phase 3) to Crawford, Murphy & Tilly, Inc., of Rockford, … $1.23M Rockford, IL ends Dec 31, 2027 Award of Engineering Agreement: 15th Avenue over Rock River Bridge Replacement (Construction Engineering) to Crawford, Murphy & Tilly, Inc., of Rockfo… $2.37M Rockford, IL Approve the award of Work Order 22-067-WATER-26-02, Construction Engineering Services - Maplebrook Phase II Water Main Improvements, to Crawford, Murp… $182K Naperville, IL Committee recommends approval of the Engineering Agreement Supplement #1 (Land Acquisition): 11th Street Corridor Improvements (IDOT Section) to Crawf… $1.20M Rockford, IL

All 18 records for Crawford, Murphy & Tilly, Inc →

Committee
City Council
Introduced
January 13, 2026
On agenda
February 3, 2026
Passed
February 3, 2026

Where it was heard

City Council Feb 3, 2026 approved