Sanitary Sewer Repair - 902 East St. Charles Road Request for a waiver of bids and award of a contract to John Neri Construction Company in the amount of $29,953.49. The depth of the sewer main and length of repair is out of the capabilities of the Village owned equipment. John Neri Construction Company has been the Village's emergency repair contractor and has proven to be reliable and responsive in these types of repairs. (DISTRICTS #4 & #5)

Bid Passed Introduced July 7, 2026

What this record is

Held by
John Neri Construction Company 12 records across this site
Amount
$30K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

John Neri Construction Company also holds

Emergency Response Water and Sewer Repairs, John Neri Construction Company, Change Order No. 1 Reflecting an increase to the contract with John Neri C… $50K Lombard, IL FY2026 Emergency Water and Sewer Repairs Request for a waiver of bids and award of a contract to John Neri Construction Company in an amount not to ex… $75K Lombard, IL Lombard Meadows - Phase IV - Final Balancing Change Order No. 2 Reflecting an increase to the contract with John Neri Construction Company in the amou… $1K Lombard, IL Waiver of Bids - John Neri Construction Company Request for a waiver of bids and award of a contract to John Neri Construction Company in an amount no… $29K Lombard, IL Highland Avenue Sewer Separation, Final Balancing Change Order No. 2 Reflecting an increase to the contract with John Neri Construction Company in the… $82K Lombard, IL

All 12 records for John Neri Construction Company →

Committee
Village Board of Trustees
Requested by
Public Works Department
Introduced
July 7, 2026
Passed
July 16, 2026

Where it was heard

Village Board of Trustees Jul 16, 2026 approved Pass