Sanitary Sewer Lining Program Change Order No. 1 Reflecting an increase of $17,872.00 to the contract with Performance Pipeline, Inc. The revised contract amount reflects additional work for the Cured-In-Place lining of a sanitary sewer located on South Lewis Avenue just south of South Broadway Avenue. (DISTRICT #5)

Resolution On Consent Agenda Introduced April 19, 2024

What this record is

Held by
Performance Pipeline, Inc
Amount
$18K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Village Board of Trustees
Requested by
Public Works Department
Introduced
April 19, 2024
Passed
May 16, 2024
Enacted
May 16, 2024
Enactment no.
R 28-24

Where it was heard

Village Board of Trustees May 16, 2024 adopted Pass Public Works & Environmental Concerns May 14, 2024 recommended to the Board of Trustees for approval Pass