Charles Lane Basin Improvements, Design Engineering, Amendment No. 3 Approving a contract amendment with Engineering Resource Associates in the amount of $46,400.00 for Full Equation (FEQ) modeling as required by DuPage County to consider approving any proposed improvements to the Charles Lane Basin. The purpose of the project is to reduce the frequency of flooding on Finley Road and Charles Lane. (DISTRICT #1)

Resolution Passed Introduced April 4, 2024

What this record is

Held by
Engineering Resource Associates 8 records across this site
Amount
$46K
Runs until
no end date published in this record
Type
amendment
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Engineering Resource Associates also holds

Engineering Resource Associates Inc. PO 6522-1-SERV is decreasing in the amount of $92,470.59 and closing due to purchase order expiring. $92K DuPage County, IL Charles Lane Basin Improvements, Design Engineering - Amendment No. 4 Approving a contract amendment with Engineering Resource Associates in the amoun… $47K Lombard, IL Approve the award of Option Year #1 for RFP 22-274, Riverwalk Design Consultant, to Engineering Resource Associates, Inc. for an amount not to exceed … $400K Naperville, IL Waive the applicable provisions of the Naperville Procurement Code and award Procurement 25-077, East Highland Area Improvements, to Engineering Resou… $209K Naperville, IL Approval of DCEO contract authorization with Engineering Resource Associates, Inc. Warrenville, Illinois for technical support services Lake County, I… $100K Lake County, IL

All 8 records for Engineering Resource Associates →

Committee
Village Board of Trustees
Requested by
Public Works Department
Introduced
April 4, 2024
Passed
April 18, 2024
Enacted
April 18, 2024
Enactment no.
R 18-24

Where it was heard

Village Board of Trustees Apr 18, 2024 adopted Pass