Joint resolution authorizing execution of a contract with Bolder Contractors, Inc., of Cary, Illinois, in the amount of $7,020,250 for the Vernon Hills West Pump Station Force Main Replacement Project and an emergency appropriation of $7,020,250 of Public Works reserve funds.

resolution Passed Introduced July 2, 2025

What this record is

Held by
Bolder Contractors, Inc 2 records across this site
Amount
$7.02M
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Bolder Contractors, Inc also holds

Joint resolution authorizing execution of a contract with Bolder Contractors, Inc., of Cary, Illinois, in the amount of $7,936,226 for the Saunders Ro… $7.94M Lake County, IL
Committee
Public Works and Transportation Committee
Requested by
Public Works
Introduced
July 2, 2025
Passed
August 12, 2025