docketcity.com
ID-2030-20

Award of Contract for the Garnsey Park Sanitary Sewer Rehabilitation Program to Hoerr Construction Inc. in the Amount of $3,221,383.00 and Amendment No. 1 to the 2025 Sanitary Sewer Rehabilitation Professional Services Agreement with RJN Group for an Amount Not to Exceed of $263,600.00

Contracts Agenda Ready Introduced January 27, 2025

What this record is

Held by
Hoerr Construction Inc 21 records across this site
Amount
$3.22M
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Hoerr Construction Inc also holds

Sewer Lining Program, Change Order No. 1 Reflecting an increase to the contract with Hoerr Construction, Inc. in the amount of $51,610.00. This increa… $52K Lombard, IL Subject: Bid Opening Results for Contract 2026-WW-SS-03, Sanitary Sewer Lining Project Staff Recommendation: To Approve Fiscal Note: Lowest responsive… $351K Racine, WI Recommendation for the approval of a contract with Hoerr Construction, Inc., for the Prairie Avenue Pipe Rehabilitation Project, for Stormwater Manage… $48K DuPage County, IL ends Nov 30, 2026 Approve the award of Change Order #1 to Contract 25-047, Sanitary Sewer Mainline Cleaning, to Hoerr Construction, Inc. for the amount not to exceed $2… $225K Naperville, IL Sanitary Sewer Lining Program Request for a waiver of bids and award of a contract to Hoerr Construction, Inc., the lowest proposal of four (4) receiv… $888K Lombard, IL

All 21 records for Hoerr Construction Inc →

Committee
Public Service Committee
Requested by
Public Utilities
Introduced
January 27, 2025
On agenda
February 3, 2025

Where it was heard

Public Service Committee Feb 3, 2025