docketcity.com
95-25

Ordinance Amending the 2024 Annual Budget for the Combined Sewer Overflow Long Term Control Plan Phase IV- Eastside and Westside Combined Sewer Overflow Regulators Project to D Construction in the Amount of $2,400,000.00 and Approve Payment of Pay Request No. 6 in the Amount of $2,663,549.96

Ordinance Passed Introduced January 23, 2025
Committee
City Council Meeting
Requested by
Public Utilities
Introduced
January 23, 2025
On agenda
February 4, 2025
Passed
February 4, 2025

Where it was heard

City Council Meeting Feb 5, 2025 City Council Meeting Feb 4, 2025 adopt Pass Pre-Council Meeting Feb 3, 2025