docketcity.com
315-24

Approve Change Order No. 2 for the Olympic Boulevard Improvements to D Construction Inc. reducing the amount by ($409,100.82) - Section No. 21-00544-00-PV

Consent Agenda Passed Introduced June 21, 2024

What this record is

Held by
D Construction Inc 12 records across this site
Amount
$409K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

D Construction Inc also holds

Approval of Change Order No. 2 for the 2024 Sidewalk / Curb Replacement Project- Central Joliet to D Construction Inc., in the Amount of $17,884.00 $18K Joliet, IL Award of Contract No. 2921-0126 for the Larkin (Theodore - Glenwood) Water Main Improvements Project to D Construction Inc. in the Amount of $9,302,06… $9.30M Joliet, IL Approval of Change Order No. 1 for the North Downtown Water Main Improvements Project on behalf of D Construction Inc. for Adjustments to Project Comp… Joliet, IL Award of Contract for the Oneida Water Main Improvements Project to D Construction Inc. in the Amount of $2,527,299.93 $2.53M Joliet, IL Approval of Change Order No. 4 for the Houbolt Road (US Route 6 - I-80) Roadway Reconstruction Project - MFT Section No. 16-00503-00-PV to D Construct… $1.81M Joliet, IL

All 12 records for D Construction Inc →

Committee
City Council Meeting
Requested by
Public Works
Introduced
June 21, 2024
On agenda
July 2, 2024
Passed
July 2, 2024

Where it was heard

City Council Meeting Jul 2, 2024 approve Pass Pre-Council Meeting Jul 1, 2024