docketcity.com
SM-P-0019-25

Recommendation for the approval of a contract with Hoerr Construction, Inc., for the 90th & Kaye Drainage Improvement Project, for Stormwater Management, for the period of September 9, 2025 through November 30, 2025, for a contract total amount not to exceed $30,845; per lowest responsible bid #23-065-PW. (Grant Funded)

Stormwater Requisition $30,000.01+ Adopted Introduced August 20, 2025

What this record is

Held by
Hoerr Construction, Inc 21 records across this site
Amount
$31K
Runs until
November 30, 2025 already ended date quoted from the award document
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Hoerr Construction, Inc also holds

Sewer Lining Program, Change Order No. 1 Reflecting an increase to the contract with Hoerr Construction, Inc. in the amount of $51,610.00. This increa… $52K Lombard, IL Subject: Bid Opening Results for Contract 2026-WW-SS-03, Sanitary Sewer Lining Project Staff Recommendation: To Approve Fiscal Note: Lowest responsive… $351K Racine, WI Recommendation for the approval of a contract with Hoerr Construction, Inc., for the Prairie Avenue Pipe Rehabilitation Project, for Stormwater Manage… $48K DuPage County, IL ends Nov 30, 2026 Approve the award of Change Order #1 to Contract 25-047, Sanitary Sewer Mainline Cleaning, to Hoerr Construction, Inc. for the amount not to exceed $2… $225K Naperville, IL Sanitary Sewer Lining Program Request for a waiver of bids and award of a contract to Hoerr Construction, Inc., the lowest proposal of four (4) receiv… $888K Lombard, IL

All 21 records for Hoerr Construction, Inc →

Committee
Stormwater Management Committee
Introduced
August 20, 2025
On agenda
September 2, 2025
Passed
September 9, 2025

Where it was heard

Finance Committee Sep 9, 2025 Approved Pass DuPage County Board Sep 9, 2025 Approved Pass Stormwater Management Committee Sep 2, 2025 Approved and Sent to Finance