Recommendation for the approval of a contract to CDM Smith, Inc., to provide professional construction oversight for the replacement of the switchgear and generator at the Power Plant, bidding assistance and construction oversight to replace the generator controls at the Standby Power Facility, and on-call electrical engineering services, for Facilities Management, for the period of November 24, 2026 through November 30, 2030, for a total contract amount not to exceed $768,000. Professional Services (Architects, Engineers and Land Surveyors) vetted through a qualification-based selection process in compliance with the Illinois Local Government Professional Services Selection Act, 50 ILCS 510/ .01 et seq.

FM Requisition $30,000.01+ Sent to Finance Introduced November 16, 2026

What this record is

Held by
CDM Smith, Inc 119 records across this site
Amount
$768K
Runs until
November 30, 2030 4 years away date quoted from the award document
Type
contract
Field
Professional services
Compared to
$165K – $762K the middle half of 79 other CDM Smith, Inc contracts; median $425K

professional services contracts in IL that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

CDM Smith, Inc also holds

Request for Approval of Amendment No. 2 to the Professional Services Agreement with CDM Smith Inc. of Albuquerque, NM (RFP No. 25098); and <br><br>1. … $330K Santa Fe, NM ends Jun 18, 2028 Subject: Consideration of a Professional Services Contract with CDM Smith for the Design and Bidding for the treatment upgrades at the Racine Water Tr… Racine, WI Subject: Consideration of Amendment No. 4 for Construction-Related Services (CRS) Contract with CDM Smith related to Contract W-23-6, Water Treatment … $266K Racine, WI [Previously discussed] Agreement for Water Treatment Plant Improvements with CDM Smith, Inc. (Omnibus Item) Western Springs, IL For Possible Approval of Addendum No. 1 to the Professional Services Contract with CDM Smith, Inc. for the Fernley Water Treatment Plant Expansion & I… Fernley, NV

All 119 records for CDM Smith, Inc →

Committee
Public Works Committee
Introduced
November 16, 2026
On agenda
November 24, 2026
Passed
November 24, 2026

Where it was heard

Finance Committee Nov 24, 2026 Approved Pass DuPage County Board Nov 24, 2026

Watch what DuPage County buys

This is one award. DuPage County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top