Recommendation for the approval of a contract to Connelly Electric Co., to furnish and install a replacement switchgear, at the Power Plant, for Facilities Management, for the period of May 13, 2025 through May 12, 2026, for a total contract amount not to exceed $324,300; per lowest responsible bid #25-057-FM.

FM Requisition $30,000.01+ Adopted Introduced April 27, 2025

What this record is

Amount
$324K
Runs until
May 12, 2026 already ended date quoted from the award document
Type
contract
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Public Works Committee
Requested by
Facilities Management
Introduced
April 27, 2025
On agenda
May 6, 2025
Passed
May 13, 2025

Where it was heard

Finance Committee May 13, 2025 Approved Pass DuPage County Board May 13, 2025 Approved Pass Public Works Committee May 6, 2025 Approved and Sent to Finance Pass