FM-P-0022-25
Recommendation for the approval of a contract to Connelly Electric Co., to furnish and install a replacement switchgear, at the Power Plant, for Facilities Management, for the period of May 13, 2025 through May 12, 2026, for a total contract amount not to exceed $324,300; per lowest responsible bid #25-057-FM.
What this record is
- Amount
- $324K
- Runs until
- May 12, 2026 already ended date quoted from the award document
- Type
- contract
- Field
- Utilities & energy
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Public Works Committee
- Requested by
- Facilities Management
- Introduced
- April 27, 2025
- On agenda
- May 6, 2025
- Passed
- May 13, 2025