14-0059

Approval for the Mayor and/or City Administrator to sign a contract with Layne Heavy Civil, Inc. for construction of the Roswell Water Treatment Plant (WTP) in the amount of $14,570,391 and an additional $150,000 in contingency for a total contract amount of $14,720,391 and approval of Budget Amendment 50743200-02-24-2014 authorizing a transfer from the Stormwater Fund to the Water Fund in the amount of $50,000 for the Stormwater Fund's share of the construction of displaced operational storage. Presented by Stuart Moring, Director of Public Works/Environmental

General Item Passed Introduced February 10, 2014
Committee
Mayor and City Council
Requested by
Environmental and Public Works Department
Introduced
February 10, 2014
On agenda
February 24, 2014
Passed
February 24, 2014