14-0059
Approval for the Mayor and/or City Administrator to sign a contract with Layne Heavy Civil, Inc. for construction of the Roswell Water Treatment Plant (WTP) in the amount of $14,570,391 and an additional $150,000 in contingency for a total contract amount of $14,720,391 and approval of Budget Amendment 50743200-02-24-2014 authorizing a transfer from the Stormwater Fund to the Water Fund in the amount of $50,000 for the Stormwater Fund's share of the construction of displaced operational storage. Presented by Stuart Moring, Director of Public Works/Environmental
- Committee
- Mayor and City Council
- Requested by
- Environmental and Public Works Department
- Introduced
- February 10, 2014
- On agenda
- February 24, 2014
- Passed
- February 24, 2014