25-0978

Request approval of a recommended proposal - Public Works, 25RFP021025K-CRB, Progressive Design/Build for Boat Rock Road Sanitary Sewer Extension, Phase 1 in an amount not to exceed $637,000.00 with Garney + Gresham Smith (Atlanta, GA) to provide progressive design services necessary to deliver a 80% design drawing and a guaranteed maximum price (GMP) associated with completing the construction and design of the sanitary sewer facilities under this project. Effective upon execution of the contract for 180 days following the issuance of the Notice to Proceed. (APPROVED)

CM Action Item - Health and Human Services Passed Introduced October 20, 2025
Committee
Board of Commissioners
Requested by
Public Works
Introduced
October 20, 2025
On agenda
December 17, 2025
Passed
December 17, 2025

Where it was heard

Board of Commissioners Dec 17, 2025 approve Pass