25-0608
Request approval of an Intergovernmental Agreement (IGA) between Fulton County, GA and the City of Roswell, GA for water main relocations associated with the road improvements to Hardscrabble Road Project in the City of Roswell, GA, in an estimated amount of $431,490.00. Effective upon approval and continue through December 31, 2027 unless amended. (APPROVED)
What this record is
- Amount
- $431K
- Runs until
- December 31, 2027 1 years away date quoted from the award document
- Type
- contract
- Field
- Construction
See everything else expiring in this field →
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of Commissioners
- Requested by
- Public Works
- Introduced
- February 12, 2025
- On agenda
- August 20, 2025
- Passed
- August 20, 2025