docketcity.com
25-0570

Request approval of Guaranteed Maximum Price (GMP) - Department Public Works, 23RFP139070K-JAJ, Progressive Design-Build Services for Campbellton Road Pump Station and Force Main in an amount not to exceed $20,332,906.00 with Sol Construction, LLC (Atlanta, GA), to perform all final design and construction activities associated with the installation of a new pump station and associated force main pipelines to serve South Fulton County. Effective upon issuance of the Notice to Proceed (NTP) with work to be completed within 24 months of the issuance of the NTP. (APPROVED)

CM Action Item - Health and Human Services Passed Introduced June 18, 2025
Committee
Board of Commissioners
Requested by
Public Works
Introduced
June 18, 2025
On agenda
August 6, 2025
Passed
August 6, 2025

Where it was heard

Board of Commissioners Aug 6, 2025 approve Pass