Request approval of a Resolution of the Fulton County Board of Commissioners to accept the City of Atlanta’s selection of Brown and Caldwell | SL King as the winning bidder of its procurement for program management services for the Tom Lowe Water Treatment Plant conducted on behalf of the Atlanta Fulton County Water Resources Commission (“AFCWRC”); to authorize the AFCWRC to enter into a contract with Brown and Caldwell | SL King for Program Management Services; to approve the expenditure of Fulton County Capital Improvement Program Funds for such services in the amount of $2.5 million per year for the initial three year term; to authorize the County Manager to approve the agreement as to content and the County Attorney to approve the agreement as to legal form; and for other purposes. (APPROVED)
What this record is
- Held by
- Brown and Caldwell 24 records across this site
- Amount
- $2.50M
- Runs until
- August 9, 2027 296 days — goes back out to bid date calculated from a contract term stated in the record, not quoted directly
- Type
- purchase
- Compared to
- $113K – $2.50M the middle half of 15 other Brown and Caldwell contracts; median $248K
professional services contracts in GA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Brown and Caldwell also holds
Board approval of Task Order No. 11 with Brown and Caldwell under the Standard Services Agreement for Water and Sewer Engineering Services As-Needed (… Board consideration and approval of Task Order No. 11 with Brown and Caldwell under the Standard Services Agreement for Water and Sewer Engineering Se… Resolution No. 3034 - Ratifyng Amendment No. 3 to Task Order No. 2 with Brown and Caldwell for the Water Treatment Plant Improvement Project Personal Services Agreement with Brown and Caldwell, Inc. for the NPDES MS4 and TMDL Support (PS 26-007) Board approval of Task Order No. 10 with Brown and Caldwell under the Standard Services Agreement for Water and Sewer Engineering Services As-Needed (…All 24 records for Brown and Caldwell →
- Committee
- Board of Commissioners
- Requested by
- Public Works
- Introduced
- August 9, 2024
- On agenda
- September 4, 2024
- Passed
- September 4, 2024
Where it was heard
Board of CommissionersWatch what Fulton County buys
This is one award. Fulton County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.