24-0484
Request approval of a recommended proposal - Public Works, 23RFP139070K-JAJ, Progressive Design/Build Services for Campbellton Pump Station and Force Main in an amount not to exceed $1,918,000.00 with Sol Construction, LLC to deliver an 80% design with a guaranteed maximum price (GMP) associated with the design and construction of the Campbellton Pump Station and Force Main effective upon issuance of the Notice to Proceed for 180 consecutive days. (APPROVED)
- Committee
- Board of Commissioners
- Requested by
- Public Works
- Introduced
- March 8, 2024
- On agenda
- July 10, 2024
- Passed
- July 10, 2024