24-0349

Request approval to extend an existing Contract - Public Works Department, 21RFP131557K-DB, Design/Build Services for Big Creek Water Reclamation Facility (WRF) Standby Generator System Project with the Georgia Power Company (Atlanta, GA) for an extension of time to provide installation and testing for power generation facilities at the Big Creek WRF. This request is for an additional 89 days for the expansion and upgrade. Effective upon BOC approval. (APPROVED)

CM Action Item - Health and Human Services Passed Introduced January 3, 2024
Committee
Board of Commissioners
Requested by
Public Works
Introduced
January 3, 2024
On agenda
May 15, 2024
Passed
May 15, 2024

Where it was heard

Board of Commissioners May 15, 2024 approve Pass