2024-1052

Commission District(s): All CO - Change Order No. 1 to Contract No. 1272495 Sanitary Sewer Chemical Root Control (Three (3) Year Multiyear Contract): for use by the Department of Watershed Management (DWM). This contract consists of treating portions of the County’s gravity sewer system with a chemical root control herbicide. This request is to increase the contract amount. Awarded to Duke’s Root Control, Inc. Amount Not To Exceed: $3,950,000.00.

Resolution Action Introduced August 16, 2024

What this record is

Held by
Duke’s Root Control, Inc 17 records across this site
Amount
$3.95M
Runs until
August 16, 2027 349 days — goes back out to bid calculated from the contract term stated in the record
Type
award
Field
Construction

See everything else expiring in this field →

Read automatically from the title of the official record. The source document below is authoritative.

Duke’s Root Control, Inc also holds

Sewer Root Control Program FY2026 Request for a waiver of bids and award of a contract to Duke's Root Control, Inc. of Syracuse, New York, in an amoun… $54K Lombard, IL To authorize the Director of Columbus Water & Power to enter into a contract with Duke’s Root Control, Inc. for sewer root control services for the Di… $225K Columbus, OH Adoption of a Resolution Awarding a $658,184.20 Contract to Duke's Root Control Inc. for the FY2026-2029 Sanitary Sewer Root Control Project, and Auth… $658K Burlingame, CA A Resolution accepting the bid of Duke’s Root Control, Inc., in the amount of $172,600, for the Flow Monitoring, for the Div. of Water Quality, and au… $173K Lexington-Fayette, KY Three-Year Term Contract with Seven-Year Renewal Options for Sewer, Manhole, Siphon Cleaning, Video and Repair Services for the Water Resources Depart… $2.00M Mesa, AZ ends Nov 20, 2028

All 17 records for Duke’s Root Control, Inc →

Committee
Board of Commissioners
Requested by
Purchasing & Contracting
Introduced
August 16, 2024
On agenda
November 12, 2024
Passed
November 12, 2024

Where it was heard

Board of Commissioners Nov 12, 2024 Approved Pass Committee of the Whole Oct 24, 2024 Board of Commissioners Oct 22, 2024 Deferred Pass Committee of the Whole Oct 15, 2024 Accepted to the BOC agenda and assigned