2025-226
Discussion of the Award of the Ridge Pine Elevated Tank and Booster Pump Station Project to Phoenix Fabricators & Erectors, LLC in the Amount of $13,237,000 - City Engineer Bethany Watson
What this record is
- Held by
- Phoenix Fabricators & Erectors, LLC 3 records across this site
- Amount
- $13.2M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Phoenix Fabricators & Erectors, LLC also holds
Discussion and Possible Action on the Award of the Ridge Pine Elevated Tank and Booster Pump Station Project to Phoenix Fabricators & Erectors, LLC in… ORDER awarding the ARPA/MCWI bid for the Espy Avenue Elevated Water Tank project to the lowest and best bidder Phoenix Fabricators & Erectors, Inc., f…- Committee
- City Council
- Introduced
- May 21, 2025
- On agenda
- June 5, 2025