Approval of Value Engineering and Contract Amendment for the removal of Landscaping and Hardscape Services on the Oxford Road Improvements/ Extension project CC-5744-24/GCM, resulting in a deductive Change Order. District4 - Lockhart (Tawny Olore, Public Works Director)

Consent Item Passed Introduced July 31, 2026
Committee
Board of County Commissioners
Requested by
Administrative Services
Introduced
July 31, 2026
On agenda
August 11, 2026
Passed
August 11, 2026

Where it was heard

Board of County Commissioners Aug 11, 2026 approve Pass