Approve Modification No. 2 to Consultant Services Authorization (CSA) 18-060-03 with Jones Edmunds & Associates, Inc for the Crooked Lake Park Receivership - Wastewater Treatment Facility (WWTF) Abandonment and Lift Station Replacements project ($30,695.26 one-time expense); and approve a CIP amendment and budget transfer to reconcile the FY 25 project budget ($1,050,000 one-time transfer).

Consent Agenda Passed Introduced August 28, 2025
Committee
Board of County Commissioners
Requested by
Utilities
Introduced
August 28, 2025
On agenda
October 7, 2025
Passed
October 7, 2025

Where it was heard

Board of County Commissioners Oct 7, 2025 Approved Pass