docketcity.com
25-0068

Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).

Consent Agenda Passed Introduced January 10, 2025

What this record is

Held by
Vogel Brothers Building Co
Amount
$893K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of County Commissioners
Requested by
Utilities
Introduced
January 10, 2025
On agenda
February 4, 2025
Passed
February 4, 2025

Where it was heard

Board of County Commissioners Feb 4, 2025 Approved Pass