25-0068
Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).
What this record is
- Held by
- Vogel Brothers Building Co
- Amount
- $893K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Board of County Commissioners
- Requested by
- Utilities
- Introduced
- January 10, 2025
- On agenda
- February 4, 2025
- Passed
- February 4, 2025