docketcity.com
24-2057

Approve construction contract with Applied Drilling Engineering, Inc. for the East Regional Utility Service Area Alternative Water Supply Receiving Facility Upper Floridan Aquifer Well project (one-time expense of $1,000,000.00 from American Rescue Plan Funds and $49,632.00 from Connection Fee Funds)

County Manager Passed Introduced October 22, 2024

What this record is

Held by
Applied Drilling Engineering, Inc 4 records across this site
Amount
$1.00M
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Applied Drilling Engineering, Inc also holds

Award of bid to Applied Drilling Engineering, Inc. for Chesnut Park managed aquifer recharge well drilling and completion of subsurface testing Pinellas County, FL Change Order No. 1 to the agreement with Applied Drilling Engineering, Inc. for the William E. Dunn Water Reclamation Facility Exploratory Well Projec… Pinellas County, FL Award of bid to Applied Drilling Engineering, Inc. for the William E. Dunn Water Reclamation Facility Exploratory Well Project. Pinellas County, FL
Committee
Board of County Commissioners
Requested by
Utilities
Introduced
October 22, 2024
On agenda
November 5, 2024
Passed
November 5, 2024

Where it was heard

Board of County Commissioners Nov 5, 2024 Approved Pass