Change Order No. 1 to the agreements to increase the upset limit with Centennial Contractors Enterprises, Inc., Harbour Construction, Inc., Johnson-Laux Construction, and New Vista Builders Group, LLC for requirements of Job Order Contracting for construction services...label Recommended Action:..Recommended Action Approval of Change Order No. 1 to the agreements to increase the contract upset limits with Centennial Contractors Enterprises, Inc., Harbour Construction, Inc., Johnson-Laux Construction, and New Vista Builders Group, LLC for requirements of Job Order Contracting for construction services. · This contract provides Job Order Contracting for facility maintenance, repair and minor construction. This request is to increase the upset limit of each agreement to effect work that is ready to process. Budgeted funds are available; these agreements are the mechanism to process work that is scoped and ready to go such as roof replacements, office remodel projects, multiple projects at the County Detention center and other assorted projects for Board of County Commissioner departments and other Constitutional Officers. · This contract was competitively solicited and awarded by the Board of County Commissioners on August 10, 2021 for a five year term through August 9, 2026. Change Order No. 1 increases the 4 contractors $3,000,000.00 each for a total combined increase of $12,000,000.00 and a revised contract total of $36M. · For funding information See RecommendedAction_25-0742A.pdf document that is attached. Contract No. 21-0324-CP; in the amount of $3,000,000.00 through August 10, 2026. This Change Order is an increase of $12,000,000.00 to the upset limit of the contract; Authorize the Chairman to sign and the Clerk of the Circuit Court to attest...Body Strategic Plan: Foster Continual Economic Growth and Vitality 4.4 Invest in infrastructure to meet current and future needs Deliver First Class Services to the Public and Our Customers 5.3 Ensure effective and efficient delivery of county services and support Summary:..Summary Change Order No. 1 to the Agreement, increasing the upset limits with Centennial Contractors Enterprises, Inc., Harbour Construction, Inc., Johnson-Laux Construction, and New Vista Builders Group, LLC for requirements of Job Order Contracting for construction services $3,000,000.00 each for a total combined increase of $12,000,000.00 and a revised contract total of $36M..

Contract/Agreement Passed Introduced May 7, 2025

What this record is

Held by
Centennial Contractors Enterprises, Inc., Harbour Construction, Inc
Amount
$3.00M
Runs until
August 9, 2026 already ended date quoted from the award document
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Construction and Property Management
Requested by
Purchasing
Introduced
May 7, 2025
On agenda
June 17, 2025
Passed
June 17, 2025

Where it was heard

Board of County Commissioners Jun 17, 2025 approved Pass